Project management is something that we will never ever get to master. The tools, the roles, and responsibilities, the approaches, or the methodology that we use in project management keep evolving with change. Even then, there are a lot of things that we need to be aware of and master. This project management quiz will help you be aware of certain aspects of project management.

Let’s get started with a project management quiz with answers.

The EVMS term that represents the value of work actually accomplished is:

Select one:
a. PV
b. EV
c. AC
d. BAC

If PV = $100, EV = $200 and AC = $300, the status is:

Select one:
a. Over budget and behind schedule
b. Over budget and ahead of schedule
c. Under budget and behind schedule
d. Under budget and ahead of schedule

Consider the following: BAC = $1000, VAC = <$200>, and AC = $400. Therefore EV = _.

Select one:
a. $ 480
b. $ 600
c. $ 800
d. Cannot be determined

The best source of revenue for a customer-requested scope change is:

Select one:
a. A customer-funded contract amendment
b. Management reserve
c. Undistributed budget
d. Profits

A common cause for a favorable SV but unfavorable CV might be:

Select one:
a. Using lower salaried workers
b. Using overtime
c. Using less expensive raw materials
d. All of the above

An S-Curve plots:

Select one:
a. Schedule variance as a function of time
b. Work package schedules as a function of time
c. Cumulative cost as a function of time
d. None of the above

Earned value measurement systems must be capable of:

Select one:
a. Measuring resources consumed
b. Measuring status and accomplishment
c. Provide a basis for diagnosis and replanning
d. All of the above

At project initiation:

Select one:
a. Few cost reduction opportunities exist and the cost of each change is large
b. Few cost reduction opportunities exist and the cost of each change is low
c. Many cost reduction opportunities exist and the cost of each change is high
d. Many cost reduction opportunities exist and the cost of each change is low

The establishment of all of the charge numbers for a project is called the:

Select one:
a. Work package codes
b. Code of accounts
c. Summation of charge numbers
d. Cost accounts

In which type of project report would we most likely find EAC and ETC?

Select one:
a. Performance
b. Status
c. Forecast
d. Exception

Answers

  1. b
  2. b
  3. a
  4. a
  5. b
  6. c
  7. d
  8. d
  9. b
  10. c