Top 10 Project Management Quiz Questions With Answers

Top 10 Project Management Quiz Questions With Answers

Welcome to the world of project management, where efficiency and organization reign supreme! Whether you’re a seasoned project manager or a budding professional eager to delve into the intricacies of successful project execution, this quiz is designed just for you. In the fast-paced realm of project management, staying on top of the latest trends and methodologies is crucial.

Our Top 10 Project Management Quiz Questions With Answers is a fun and informative way to test your knowledge and sharpen your skills. From project planning to risk management, these questions cover the essentials. So, buckle up and get ready to explore the dynamic landscape of project management, where each question is a stepping stone towards mastering the art of successful project delivery.

So, let’s move on to the Top 10 Project Management Quiz Questions With Answers

  1. Q1. Critical Chain method was developed to address several problems that are common in organizations that use traditional project scheduling. Which of the following describes a common problem addressed by the critical chain method?

    Select one:
    a. Many team members work best when multitasking
    b. Many team members tend to use all of the time available for an activity rather than completing it early.
    c. Many team members render overly optimistic estimates of the time it will take them to complete project activities.
    d. Many team members work solely on a single task until it is complete – impeding work on other related activities.

  2. Q2. Project managers must often face the challenge of compressing the project schedule. All of the following actions can be taken to reduce the duration of the critical path EXCEPT:

    Select one:
    a. Reduce the project scope and /or quality.
    b. Partially overlap sequential activities by using time leads.
    c. Overlap sequential activities using finish-to-finish, start-to-start, or start-to-finish relationships.
    d. Use the float in critical path activities

  3. Q3. A common tool project teams use is a responsibility assignment matrix (RAM). Typically, this chart will depict:

    Select one:
    a. the hierarchical organizational reporting structure.
    b. the early start and early finish, and late start and late finish, of each schedule activity.
    c. all the work packages and the resources assigned for various responsibilities regarding each work package.
    d. the duration of each activity.

  4. Q4. Project managers often confront the challenge of reducing excessive time commitments and overloads among project resources. All of the following methods can be used to reduce work overloads EXCEPT:

    Select one:
    a. Reassign certain activities to other workers.
    b. Reorder activities when logically feasible.
    c. Require all project resources to work overtime
    d. Split an activity into two activities and delay the second part.

  5. Q5. Critical Chain Project Management (CCPM) attempts to keep the most highly demanded resource busy on critical chain activities but not overloaded.

    Select one:
    a. True
    b. False

  6. Q6. When resource overloads are extreme, project managers may need to consider the acquisition of additional resources, reductions in scope or extensions to the project schedule.

    Select one:
    a. True
    b. False

  7. Q7. Even when a project team does not identify individual activities, it will still need to determine how many resources and what knowledge and skills each needs to complete the project.

    Select one:
    a. True
    b. False

  8. Q8. Crashing is a project schedule compression technique that expedites a project by executing activities at the same time that ordinarily would be done one after the other.

    Select one:
    a. True
    b. False

  9. Q9. While a “RACI” chart may be very useful for assigning activities to core team members and project managers, it should not include the subject matter experts assigned to the project.

    Select one:
    a. True
    b. False

  10. Q10. One approach to identifying which activities contribute to work overload for a particular resource is to compare the resource histogram to the Gantt chart schedule using the same timescale.

    Select one:
    a. True
    b. False

Answers (Project Management Quiz)

  1. b
  2. d
  3. c
  4. c
  5. a
  6. a
  7. a
  8. b
  9. b
  10. a